Mentors

Name

Time zone

Email ID

Imre Kocsis

CETkocsis.imre@vik.bme.hu

László Gönczy

CETgonczy.laszlo@vik.bme.hu

Mentee

Name

Time zone

Email ID

André Augusto

CET-1andre.augusto@tecnico.ulisboa.pt


Mentorship GitHub repository:  https://github.com/AndreAugusto11/Fabric-Ethereum-token-bridging

Deliverables

  • Report on existing bridging solutions
  • Report on asset representation solutions and mapping between Hyperledger Fabric and Ethereum.
  • Requirement Specification Document
  • Design Specification Document
  • Implementation of the Proof of Concept
  • Final presentation

Merged PR's

  • TBD

Final Project Presentation:

  • TBD

Milestones

Eval 1:

  • TBD

Eval 2:

  • TBD

Eval 3:

  • TBD

Eval 4:

  • TBD

Timeline

DoneWeekDatesTasks/PlanDeliverablesEvaluation
1June 1 to
June 12
Mentee onboarding.
Initiate research on Ethereum Token Standards.
Understand the context of the problem and the use case already defined.

-
2June 13 to
June 19
Research on existing token bridging solutions.Report on existing bridging solutions and their applicability to the use case.-

3June 20 to
June 26
Research on asset representation solutions and how they can be applied to Hyperledger Fabric and Ethereum.Report on asset representation solutions and mapping between Hyperledger Fabric and Ethereum.1st Quarter Evaluation

4June 27 to
July 3
Understand the requirements of the use case, and if Hyperledger Cactus fits the implementation platform requirements.Requirement Specification Document.-

5July 4 to
July 10
Design a solution for the problem and identify the different components.Design Specification Document.-

6July 11 to
July 17
Introduction to development platform and necessary tools for the implementation.
Midterm Evaluation

7July 18 to
July 24
Start solution implementation.
-

8July 25 to
July 31
Solution implementation.
-

9August 1 to
August 7
Solution implementation.
3rd Quarter Evaluation

10August 8 to
August 14
Solution implementation.
-

11August 15 to
August 21
Enhancements to the implementation (e.g., work on other token standards).Implementation of the Proof of Concept-

12August 22 to
August 28
Work on a demo to present the project.Demo for the final presentation of the projectFinal Evaluation