Project Plan - Fabric-Ethereum token bridging

Project Plan - Fabric-Ethereum token bridging

Mentors

Name

Time zone

Email ID

Name

Time zone

Email ID

Imre Kocsis

CET

kocsis.imre@vik.bme.hu

László Gönczy

CET

gonczy.laszlo@vik.bme.hu

Mentee

Name

Time zone

Email ID

Name

Time zone

Email ID

André Augusto

CET-1

andre.augusto@tecnico.ulisboa.pt



Mentorship GitHub repository:  https://github.com/AndreAugusto11/Fabric-Ethereum-token-bridging

Deliverables

Report on existing bridging solutions
Report on asset representation solutions and mapping between Hyperledger Fabric and Ethereum.
Requirement Specification Document
Design Specification Document
Implementation of the Proof of Concept
Final presentation

Merged PR's

Final Project Presentation:

  • TBD

Timeline

Done

Week

Dates

Tasks/Plan

Deliverables

Evaluation

Done

Week

Dates

Tasks/Plan

Deliverables

Evaluation

1

June 1 to
June 12

Mentee onboarding.
Initiate research on Ethereum Token Standards.
Understand the context of the problem and the use case already defined.



-

2

June 13 to
June 19

Research on existing token bridging solutions.

Report on existing bridging solutions and their applicability to the use case.

-

3

June 20 to
June 26

Research on asset representation solutions and how they can be applied to Hyperledger Fabric and Ethereum.

Report on asset representation solutions and mapping between Hyperledger Fabric and Ethereum.

1st Quarter Evaluation

4

June 27 to
July 3

Understand the requirements of the use case, and if Hyperledger Cactus fits the implementation platform requirements.

Requirement Specification Document.

-

5

July 4 to
July 10

Design a solution for the problem and identify the different components.

Design Specification Document.

-

6

July 11 to
July 17

Introduction to development platform and necessary tools for the implementation.



Midterm Evaluation

7

July 18 to
July 24

Start solution implementation.



-

8

July 25 to
July 31

Solution implementation.



-

9

August 1 to
August 7

Solution implementation.



3rd Quarter Evaluation

10

August 8 to
August 14

Solution implementation.



-

11

August 15 to
August 21

Enhancements to the implementation (e.g., work on other token standards).

Implementation of the Proof of Concept

-

12

August 22 to
August 28

Work on a demo to present the project.

Demo for the final presentation of the project

Final Evaluation