  • announcement: v1 release to be postponed 2 weeks

  • discussion about the release schedule

    • security checks by ourselves: march 14

    • audit by audit company might take 4-6 weeks after that

    • announcement can be done through Github page and TSC report and blog posts

      • you don't need approval from TSC for release

  • Michael Courtin is leaving the cactus project

    • at the moment, two PRs (1707, 1853) from Michael are waiting to be merged/approved

      • 1853 approved during the meeting