2022-02-28 Meeting Notes
Date
Recordings
Attendee
Discussion
announcement: v1 release to be postponed 2 weeks
discussion about the release schedule
security checks by ourselves: march 14
audit by audit company might take 4-6 weeks after that
announcement can be done through Github page and TSC report and blog posts
you don't need approval from TSC for release
Michael Courtin is leaving the cactus project
at the moment, two PRs (1707, 1853) from Michael are waiting to be merged/approved
1853 approved during the meeting