Overview

The main goal of the project is to create a documented Hedera Hashgraph package for the Cactus project, which demonstrates the interoperability between Hedera and Cactus. The documentation will benefit the community so that people can understand this project.

Mentor and Mentee

Mentor

Mentor

Mentor

Mentee

Danno Ferrin

MDT (UTC-6)

danno.ferrin@gmail.com

Peter Somogyvari

PDT (UTC-7)

peter.somogyvari@accenture.com

Si Chen (Open Source Strategies, Hyperledger Climate SIG)

Discord: Si Chen#0557

sichen@opensourcestrategies.com

Jande Vincent Shater

WAT (GMT +1)

janvinsha@gmail.com

Communication channel: Discord

Project repo: 

https://github.com/hyperledger/cactus

https://github.com/hashgraph/hedera-sdk-js

Project Plan

Schedule

Task

Deliverable

Week 1 - Week 3

Jun 1 - Jun 24

Jun 18: 1st Quarter Evaluation

  • Build Cactus.
  • Build and run one cactus example
  • Complete Hedera "Getting Started" in JS
  • Start the Hedera and Cactus integration.
  • Project Plan.
  • Skeleton for Hedera and Cactus integration.

Week 3 - Week 6

June 25 - July 13

July 13: Midterm Quarter Evaluation

  • Implement the Hedera and Cactus integration.
  • Write tests for the Hedera and Cactus integration.
  • Write documentation.
  • ~50% of the Hedera and Cactus integration package.
  • Technical documentation for the package.

Week 6 - Week 9

July 14 - August 3

Aug 3: 3rd Quarter Evaluation

  • Example of Hedera and Cactus integration.
  • Example of Hedera and another DLT integration.
  • Write tests for Hedera and Cactus integration.
  • Write tests for Hedera and another DLT integration.
  • Write documentation.
  • Completed package for Hedera and Cactus integration.
  • Examples of Hedera and Cactus integration.
  • Examples of Hedera and another DLT integration.

Week 12

Aug 4 - Aug 24

Aug 24-31: Final Evaluation

  • Wrap up documentation.
  • Final report of the project.
  • Final presentation of the project
  • Code for unit tests and integration tests. *
  • Technical documentation for the entire project.
  • Final report.
  • Final presentation.

* Will wrap up all codes-relevant stuff by Aug 5.

Timeline

Week

Task

Weekly Slide

1 (Jun 1 - Jun 10)
  • Attend onboard meeting
  • Read the project wiki page
2 (Jun 11 - Jun 17)
  • Set up environment
  • Build Cactus
  • Project Plan
  • Complete Hedera "Getting Started" in JS

3 (Jun 18 - Jun 24)

4 (Jun 25- Jul 1)

5 (Jul 2 - Jul 8)Danno is Out of Office

6 (Jul 9 - Jul 15)



7 (Jul 16 - Jul 22)

8 (Jul 23 - Jul 29)

9 (Jul 30 - Aug 5)



10 (Aug 6 - Aug 12)

11 (Aug 13 - Aug 19)

20 (Aug 20 - Aug 3)

Process

  • Communication and updates:
    • Discord and github are used as tools.