Week # | Week | Activity | Status |
0 | June 1 -June 7 | First contact with mentor and discussion of solutions. | Completed |
1-3 | June 8 - June 28 | Understand the code base and Resolve issue-3 | Completed |
4-6 | June 29 - July 12 Evaluation 1 | Resolve issue-4 | Testing |
7-8 | July 12 - July 25 | Discuss and create architecture | Completed |
9-10 | July 26 - August 8 Evaluation 2 | Integration with Aries (Integrated with Aries framework javascript) | Completed |
11-14 | August 9 - September 5 | Resolve issues and feedback given by mentors | In-Progress |
15-18 | September 6 - October 3 Evaluation 3 | Design a modular architecture | In-Progress |
19-20 | October 4 - October 17 | Start the implementation | |
21-22 | October 18 - October 31 | Discuss on future work and create a skeleton | |
23-24 | November 1 - November 14 Evaluation 4 | Complete documentation |
...