Activities and Deliverables

ScheduleActivityDeliverables

Week 1 - Week 6

Jun 1 - Jul 13

Jul 11: 1st Quarterly Evaluation
  •  Conduct a literature review on blockchain Interoperability.
  •  Typescript course;
  •  Understand the architecture of Hyperledger Cactus Connector
  •  Investigate the required tools and components for the project.
  •  Project Plan
  •  Code/Libraries Setup
  •  Submit PR for open issues on Github 

Week 7 - Week 12

Jul 13 - Aug 24

Aug 22: 2nd Quarterly


Week 13 - Week 18

Aug 24 - Oct 5

Oct 3: 3rd Quarterly Evaluation


Week 19 - Week 24

Oct 5 - Nov 13

Nov 14: 4th Quarterly Evaluation