Release Date | Cutoff Date | Release Version | Executor | Approver | Release Coordinator | Time Taken |
---|---|---|---|---|---|---|
Dec 28 (2022) | 23.1.0-beta | Gary | Beta - Not released as production ready. Will include EOF | |||
Jan 11 | 23.1.0-RCx 22.10.4 | Gary | start from main, cherry pick until done on 25th | |||
23.1.0 | Gary | Delayed due to instability. Cut from main from Feb 8, plus a few fixes | ||||
Feb 19 | 23.1.1-RC1 (Sepolia Shanghai) | Simon | Cut from main, basically 23.1.0 plus Sepolia config | |||
March 8? | ? | |||||
Volunteers
- Jiri
- Karim
- Danno
- Justin
- Gary
- Sally
- Stefan
- Lucas
- Jason