Project plan - Cactus-samples - Business Logic Plugins for Hyperledger Cactus

Project plan - Cactus-samples - Business Logic Plugins for Hyperledger Cactus


Schedule

Activity

Deliverables

Q1

Week 1 to Week 3

Conduct a literature review on Open Digital Asset protocol(ODAP) and DLT Gateway Crash Recover Mechanism

Investigate the required tools and components for the project


Set up working environment



Implement ODAP infrastructure

  • Project plan



  • Code for the working environment
  • Code for the ODAP infrastructure


  • Project system design documentation of the working environment.


  • Create github issues for ODAP

Q2

Week 4 to Week 6


Implement ODAP protocol

Design and Implement the music cross-chain app architecture


  • Code for the system


  • A system design document for the music cross-chain app.
  • Project technical documentation of the system

Q3

Week 7 to Week 9

Implement ODAP crash recovery feature - if time permits 


Find relevant cross-chain app 



Compare the solutions in terms of non-functional properties such as performance, security, usability

  • A report about the properties of similar solutions

  • Project technical documentation of the implemented tests


  • Test results of the benchmarking tool

Q4

Week 10 to Week 12

Complete technical report of the project.



Writing a research paper based on the design, implementation, and evaluation of the project

  • A cross-chain music app based on ODAP and hyperledger cactus

  • Technical report of the project
  • Academic paper reporting results