Schedule | Activity | Deliverables |
Q1 Week 1 to Week 3 | Conduct a literature review on Open Digital Asset protocol(ODAP) and DLT Gateway Crash Recover Mechanism Investigate the required tools and components for the project Set up working environment Implement ODAP infrastructure |
|
Q2 Week 4 to Week 6 | Implement ODAP protocol Design and Implement the music cross-chain app architecture |
|
Q3 Week 7 to Week 9 | Implement ODAP crash recovery feature - if time permits Find relevant cross-chain app Compare the solutions in terms of non-functional properties such as performance, security, usability |
|
Q4 Week 10 to Week 12 | Complete technical report of the project. Writing a research paper based on the design, implementation, and evaluation of the project |
|