Project plan - Support Hyperledger Fabric 3 in Fablo
Project plan - Support Hyperledger Fabric 3 in Fablo
Abstract
The overall objective of the current mentorship program is to drop support for legacy Fabric versions in Fablo (1.3, 1.4), and add support for Hyperledger Fabric v3, along with BFT consensus. Optional tasks include support for ARM architecture (Apple M1-3).
Mentors
Name | Timezone | |
---|---|---|
Jakub Dzikowski | CET | |
Piotr Hejwowski | CET |
Mentee
Name | Timezone | |
---|---|---|
Sanket Teli | GMT+5:30 | telisanket2002@gmail.com |
Project codebase:
https://github.com/hyperledger-labs/fablo
Outcomes:
- Feature + automatic tests: Fablo supports Hyperleder Fabric v3
- Feature + automatic tests: Fablo supports BFT consensus for Hyperledger Fabric v3
- Maintenance: Support for Fabric v1.3 and v1.4 is removed
Timeline:
Week | Deliverables | Status |
---|---|---|
Jun 03 - Jun 16 | Phase 1 starts - warming up and learning the code base
| Done |
Jun 17 - Jun 30 |
| In Progress |
Jul 01 - Jul 14 | Phase 2 starts - removal of support for Fabric 1.3 and 1.4
Up to this row the scope is required for Q1 evaluation. | In Progress |
Jul 15 - Jul 28 |
| |
Jul 29 - Aug 11 |
| |
Aug 12 - Aug 25 | Phase 3 starts - adding support for Fabric v3 and BFT consensus
| |
Aug 26 - Sep 08 |
| |
Sep 09 - Sep 22 |
| |
Sep 23 - Oct 06 |
| |
Oct 07 - Oct 20 | Phase 4 starts - optional tasks
| |
Oct 21 - Nov 03 |
| |
Nov 04 - Nov 17 |
|
Methodology
- Lean, iteration-based development with mentor guidance