Project Plan - One-stop shop for all-things Hyperledger
Abstract
Hyperledger India Chapter started with the https://start-here.hyperledger.org to help new developers look for contribution opportunities. The tool provides an option to see through a list of all "Good First Issues", "Open PRs" and "Releases".
The requirement, in this proposal, is to extend or improve the website to include - role-based navigation (eg. Developer, Business User, Contributor, etc) to information. The process will involve adding easy to access links or information for project documentation, community contribution guidelines, guiding (new & experienced) users towards how to start & what tasks require contribution, informing the latest happenings within the community (i.e. figuring out available events and meetups), and Calendar(s). The cherry on top of it would be to have navigations defined for different users and search capability.
The task would start with the survey on what somebody looks for within the community, understand what troubles them. The project is aimed at providing an improved user experience.
Mentors
Name | Time zone | Discord ID | Email ID |
---|---|---|---|
Arun S M | IST | arsulegai#7968 | arun.s.m.cse@gmail.com |
Vikram Sharma | IST | Sharmawiki#1283 | vikram13sharma@gmail.com |
Kamlesh Nagware | IST | knagware#6976 | kamlesh.nagware@gmail.com |
Mentee
Name | Time zone | Discord ID | Email ID |
---|---|---|---|
Niku Singh | IST | Niku#1433 | soapmactavishmw4@gmail.com nikusingh319@gmail.com |
Communication channel: Discord+ Github
Project repo: https://github.com/hyperledger-tooling/getting-started
Deployed Link: https://getting-started-flame.vercel.app/
Figma Design:
Deliverables
- Improve User Experience - From Getting Started With Hyperledger To Continuous Engagement
- Dashboard and the landing page for driving the user engagement.
- Ability to search events and happenings within the Hyperledger community.
- Find out all things project information from the user engagement portal.
Merged PR's
- TBD
- TBD
- TBD
Final Project Presentation:
Milestones
Eval 1:
- TBD
Eval 2:
- TBD
Eval 3:
- TBD
Eval 4:
- TBD
Timeline
Dates | Tasks/Plan | Status |
---|---|---|
Dates | Tasks/Plan | Status |
June 1 - June 14 | Mentee intro with the mentor. | Completed |
June 15 - June 28 | Create project plan | Completed |
June 29 - July 12 | Doing Research on users and Understanding the user problems | Completed |
July 13 - July 26 | Creating the 1st Iteration of UI | Completed |
July 27 - Aug 9 | Getting it approved by the mentors | Completed |
Aug 10 - Aug 23 | Creating 2nd Iteration of the Design | Completed |
Aug 24 - Sept 6 | Start creating the frontend | Completed |
Sept 7 - Sept 20 | Finishing off the frontend | In Progress |
Sept 21 - Oct 4 | Creating the Backend. | In Progress |
Oct 5 - Oct 18 | Connecting the Backend to frontend | In Progress |
Oct 19 - Nov 1 | Deploying the project | In Progress |
Nov 2 - Nov 12 | Final Presentation of the project | In Progress |
Methodology
TBD