Project Plan - Operate and Govern Blockchain Networks in Decentralized Way

Project Plan - Operate and Govern Blockchain Networks in Decentralized Way

Goals

Implement the new governing module with Cello.

Deliverables

User Dashboard RESTful APIs
Implement features according to cello v1.0 design spec
Documentation for newly implemented features

Timeline

The tentative timeline is as follows:

Week

Deliverables

Week 1 - Week 6 

 

Understanding Design Specifications (v1.0) of Blockchain Consortium governing with Cello
Help to migrate the user dashboard.

Week 7 - Week 12

 

Implement User Dashboard RESTful APIs (User, Network).
Improve the current documentation.

Week 13 - Week 18

Implement User Dashboard RESTful APIs (Channel, Node).
Help with the issues raised on Github.

Week 19 - Week 24

Test the workflow of the new governing module and fix possible bugs.
Write down related documentations.

Newly designed features will be incorporated during the course of the mentorship program.

Methodology

  • The evaluation takes place on a quarterly basis according to the timeline.

  • Work closely with mentors

    • Participate weekly zoom meeting

  • Help building community

    • Answer questions on Github Issues, Wechat, Rocketchat, mailing list, etc.