- Comprehensive Test Suites that covers all aspects of hyperledger caliper and ensures high test coverage
- Document details of the testing framework, test cases, and guides for future contribution to easily maintain test quality
- Implement CI/CD pipeline that automates the testing process, and ensures every contribution is thoroughly tested
- Detail the internal workings of caliper components to facilitate future contribution
Milestones
Eval 1:
- Bump up the test framework and tools to the latest version
- Fix inconsistencies in test structure
- contributor.md document detailing the test framework and tools and their uses Add a section in the
- Using an example test suite, describe the methodology to add a test suite
Eval 2:
- add test for the untested modules in the folder: caliper-core/lib/worker/rate-control/
- add test for the untested modules in the folder: caliper-core/lib/worker/tx-observers/
- add test for the untested modules in the folder: caliper-core/lib/worker/worker-message-handler
Eval 3:
- add test for the untested modules in the folder: caliper-core/lib/manager/test-observers
- add test for the untested modules in the folder: caliper-core/lib/manager/monitors/
- add test for the untested modules in this folder: caliper-core/lib/manager/orchestrators/
- add test for the untested modules in this folder: caliper-core/lib/manager/report/
Eval 4:
- work on the CI/CD and test reporting for the project
- add test for the untested modules in the folder: caliper-core/lib/common/
Timeline
Week | Task/Plan | Status |
---|---|---|
June 03 - June 23 | On-boarding/orientation sessions. Meet with the mentors, discuss project implementation details, deliverables and scope. Prepare the project plan. | |
June 24 - July 7 | Implement the points highlighted in Eval1 on in the Milestone section of this document | |
July 8 - July 19 | Implement the points highlighted in Eval1 in the Milestone section of this document | |
July 22 - July 26 | 1ST QUARTER MENTEE EVALUATION | |
July 27 - August 18 | Implement the points highlighted in Eval2 in the Milestone section of this document | |
August 19 - September 01 | implement the items in Eval2 of the Milestones section of this Document | |
September 02 - September 06 | Round up the items in Eval 2 MIDTERM EVALUATIONS | |
September 08 - September 22 | implement the items in Eval3 of the Milestones section of this Document | |
September 23 - October 19 | implement the items in Eval3 of the Milestones section of this Document | |
October 14 - October 18 | implement the items in Eval4 of the Milestones section of this Document 3RD QUARTER MENTEE EVALUATION | |
October 19 - November 10Timeline buffer. | implement the items in Eval4 of the Milestones section of this Document | |
November 11 - November 29 | FINAL MENTEE EVALUATION |
...