DatesTasks/Plan

Status

Jun 12 - Jun 26Mentee intro with the mentor. Decision on the progress of the connectorCompleted
Jun 27 - Jul 10Understanding of the current work done for polkadot in #1997 PRCompleted

Jul 11 - Jul 24

Upgrade the existing AIO to latest version of Polkadot - phase 1 (AIO)Completed
Jul 25 - Aug 7 (Jul 28 eval)Upgrade the existing AIO to latest version of Polkadot - phase 2 (test-tooling)Completed
Aug 8 - Aug 21Update the connector code for the new version - phase 1Completed

Aug 22 - Sep 4 (Aug 31 eval)

Update the connector code for the new version - phase 2Completed
Sep 5 - Sep 18Update the test cases for the new version - phase 1Completed
Sep 19 - Oct 2Update the test cases for the new version - phase 2Completed
Oct 3 - Oct 16Prometheus Integration with the connector code and test casesCompleted
Oct 16 - Oct 30 (Oct 20 eval)Architecture reference diagrams of the connectorIn ProgressCompleted
Oct 31 - Nov 6Documentation of the connector, creation of PRIn ProgressCompleted
Nov 7 - Nov 30 (Nov 30 eval)Final presentation and updated documentation

Methodology

  • TBD
  • TBD
  • TBD
Blogpost creation and PR mergeIn Progress

Methodology

  •  Understand cacti codebase and the supplychain example (to understand what functionalities is generally expected from a connector)
  •  Understand a single connector (like besu connector) and its development lifecycle (how the connector is gradually created by first having its dockerised AIO, then its test tooling, then generation of code using a master openapi spec file, and then wiring up everything alongside the creation of the main connector class and finally having the connector README docs)
  •  Creation of polkadot AIO image (part1)
  •  COMMIT - 1: Creation of polkadot AIO image (part2) (this will take up time, thus dividing into 2 parts)
  •  COMMIT - 2: Creation of polkadot test tooling
  •  Creation of polkadot connector openapi specs, basic test case and connector class with base functions (part 1)
  •  COMMIT - 3: Creation of polkadot connector openapi specs, basic test case and connector class with base functions (part 2) (This will take up significant time, thus dividing into 2 parts)
  •  Updation of the openapi specs, test cases and addition of the rest of the code as per the requirements observed in commit 3 test cases (part 1)
  •  COMMIT - 4; Updation of the openapi specs, test cases and addition of the rest of the code as per the requirements observed in commit 3 test cases (part 2) (this will take up the most time, thus dividing into 2 parts)
  •  COMMIT - 5: Creation of README.md for the connector plugin and architecture reference diagrams
  •  Creation of PR with the 5 progressive commits and incorporation of review comments
  •  Creation of final presentation/demo to showcase the work done in this project