See FAB-4379 for a template JIRA
Proposals
Weekly release cadence - CBF
- begin merge moratorium on Weds am at 8 am ET
- ensure Daily and Weekly tests are run, force repeated CR CI passes of each repository
- if significant issues found, defer release for following week (no sense killing ourselves)
- if no significant issues found, proceed with release
- create Task for weekly release, cloned from this JIRA Task
- assign a release manager to the execution (should not try to coordinate steps, this is where errors of mis-communication occur)
- begin the release process at 8am Thursdays
- on successful testing of download/images/docs review and e2e testing, spam announce email
- lift merge moratorium
Notes/Observations
...
Current Release Process
The latest Hyperledger Fabric release process can be found in the Release Process google document.