- 1 Extend get*transactions with optional parameters such as date from, date to(Protobuf + Iroha base code)
- 2 Add the optional arguments to Python Iroha library.
- 3 Add unit tests to Iroha base code
- 4 Deliver necessary docs
- 5 Add the optional arguments to Java Iroha library.
- 6 Add the optional arguments to Js Iroha library.
- 7 *Add the optional arguments to Swift Iroha library7 Present results to Iroha community
...
- h Cleanup, refactoring and debugging, adding examples to Iroha python client
- i Adding code changes to official Iroha repositories
- j Presenting results.
- k * update iroha-tui-client -if necessarily
Timeline
Week | Task/Plan | Status |
---|---|---|
June 1 - June 4 |
| done |
June 7 - June 11 | Reading Iroha code and changing protobufs. Finding database transaction queries. | done |
June 14 - June 25 |
2. Modifying python library code. 3*. Ask about date format for protobuff, with explaining existing one. 4*. Code clean. | done |
June 28 - July 2 | Modifying other queries specified in abstract. | done |
July 5 - July 9 |
| |
July 12 - July 23 |
| done |
July 26 - August 6 |
| done |
August 9 - August 13 |
| done |
August 16 - August 27 |
| done |
August 30 - Sept 3 | Extending queries: GetAccountTransactions, GetAccountAssetTransactions for RocksDB - learning codebase | done |
Sept 6 - Sept 17https://github.com/hyperledger/iroha-java/pull/83 | Pull request for Iroha java + corrections Getting familiar with iroha ios library and iroha-tui client | done |
Sept 20 - 24 | ||
Sept 27 - Oct 1 | Eval 3 | |
Oct 4 - Oct 15 | ||
Oct 18 - Oct 29 | ||
Nov 1 - Nov 5 | ||
Nov 8 - Nov 12 | Eval 4 Final evaluation and presentation of project |
...